RERA & Homebuyers

RERA Refunds With Interest: Your Right Under Section 18 in Jaipur

By Mishpat Legal Consultants

Updated

If you are in Jaipur, the following is general information on rera refunds with interest for someone in Jaipur.

Why a homebuyer's right to a refund with interest for a delayed project is unconditional.

In Newtech Promoters & Developers v State of UP (11 Nov 2021), the Supreme Court held that a homebuyer's right to a refund with interest under RERA s.18, for a developer's failure to complete and hand over possession on time, is unconditional.

A complaint seeking this relief is filed under RERA s.31 before the relevant state's Real Estate Regulatory Authority.

Typically, a homebuyer generally has a choice between seeking a refund with interest for the delay, or continuing with the project and claiming interest for the period of delay until possession is handed over, rather than being forced to accept either option.

As a general rule, rERA complaints are generally intended to proceed faster than ordinary civil litigation, with the Authority empowered to pass interim orders and the final order being executable in the manner of a civil court decree.

Where this applies in Jaipur

  • The High Court with jurisdiction is the Rajasthan High Court, Jaipur Bench.
  • Matters at the district level are generally handled at the Jaipur Metropolitan or District Court, depending on the matter.
  • The applicable regulator is RERA Rajasthan.

Documents generally involved

  • The builder-buyer agreement
  • Payment receipts showing the consideration paid
  • Any communication about the delay or possession date
  • The project's RERA registration number, if available

Common pitfalls

A few points are easy to get wrong.

  • Assuming you must show the developer was at fault beyond simply missing the committed timeline — the Supreme Court has held the s.18 refund right is unconditional on delay.
  • Filing in the wrong forum — RERA complaints go to the state Real Estate Regulatory Authority under s.31, not directly to a civil court or consumer commission, though parallel remedies can exist.
  • Not checking whether the project itself is registered under RERA, which can affect how the complaint proceeds.

For related reading, see Can a Homebuyer Use the Insolvency Process Against a Builder? and RERA and Homebuyer Rights: An Overview.

If you are weighing a decision on this, a short consultation can help map out the options.

This page is general information about the law in India and is not legal advice. The position can vary with the facts, so it is worth getting advice on your specific situation.

This page provides general information about the law in India and is not legal advice. For advice on your specific situation, please consult a qualified advocate.

FAQ

Common questions

Can I get a refund with interest if my builder delays possession?

Generally yes. The Supreme Court held in Newtech Promoters & Developers v State of UP (11 Nov 2021) that the right to a refund with interest under RERA s.18 for delayed possession is unconditional.

Have a related question?

You are welcome to reach out to discuss your situation.

Discuss your matter